On-Site Works Update: – Site access, hoarding, amenities and offices complete – Demolition/strip-out of existing levels is generally complete – Preparation for erection of tower crane underway Off-Site: – Tower crane procurement and lift date is confirmed – Planning, procurement and manufacture of structural members for extended levels is underway – Planning and procurement … Continue reading Construction Update 02/08/16