On-Site Works Update:

– Site access, hoarding, amenities and offices complete

– Demolition/strip-out of existing levels is generally complete

– Preparation for erection of tower crane underway

 

Off-Site:

– Tower crane procurement and lift date is confirmed

– Planning, procurement and manufacture of structural members for extended levels is underway

– Planning and procurement of facade and windows is underway

– Services planning, coordination and procurement is underway